Meriton Sewer and Stormwater Works - Howard Avenue

10 months ago

We have been advised that Meriton will be commencing their sewer diversion works in Howard Avenue from the 8 June 2016. These works, approved by Sydney Water, include road works on the northern side of the roadway between Pittwater Road to 10 Howard Avenue. The sewer works will be undertaken at night and are expected to take approximately 3 weeks.

Meriton will then commence their stormwater diversion works including the installation of a stormwater pipe from 29 Howard Avenue to the intersection of Pittwater Road. These works will take up the southern lane of Howard Avenue and are expected to take a further 8 weeks.

The works will be carried out by Stephen Todd Contractors (NSW). The site contact for the initial night works (from 8pm-5am) is Peter Martin 0433 331 255.

View the sewer and stormwater plans

View Meriton sewer works Traffic Management Plan - no.1