Discover what's happening

  • Project update - October 2024

    We are installing traffic calming measures along Cabbage Tree Road and on Pittwater Road near its intersection with Cabbage Tree Road in Bayview.

    Work is expected to start in early October and last about 4 weeks, weather permitting. Read more on what we are doing and how we are managing the works below.

What's happening

We are improving road safety based on a review of historical crash data and community input regarding motorist and pedestrian safety along Cabbage Tree Road and Pittwater Road, specifically near the intersection with Cabbage Tree Road in Bayview.

In response to concerns expressed by residents during community consultation and to enhance safety while mitigating the likelihood and severity of accidents, we have proposed additional traffic calming measures.

The recommended improvements supported by the Local Traffic Committee are:

  1. Installation of a raised threshold with marked cycle ways, warning and speed advisory signs on Pittwater Road near the intersection with Cabbage Tree Road.
  2. Installation of a raised threshold with warning and speed advisory signs on Cabbage Tree Road in front of No.12 and Bayview Golf Club, between Beaumont Crescent and Binnowee Place.
  3. Installation of a raised threshold with warning and speed advisory signs on Cabbage Tree Road near Annam Road in front of Bayview Golf Club and Bayview Gardens Retirement Living.
  4. Installation of a safety guard rail (25m) in front of Bayview Golf Club at the intersection of Cabbage Tree Road with Beaumont Crescent.
  5. Installation of reflective pavement markers (approximately 50m) on centrelines on Cabbage Tree Road between House o.6 Cabbage Tree Road and No.6 Binnowee Place.
  6. Installation of reflective pavement markers (approximately 35m) on centrelines on Cabbage Tree Road, south of Annam Road in front of Bayview Golf Club and Bayview Gardens Retirement Living.
  7. Installation of a raised median on Cabbage Tree Road near the intersection with Annam Road.
  8. Installation of curve warning and advisory speed signs on Cabbage Tree Road between No. 24 Cabbage Tree Road and Bayview Gardens Retirement Living.
  9. Installation of street lighting in front of No.14A Cabbage Tree Road.
  10. Installation of profile line marking (Audio Tactile) – Type A and retro reflective pavement markers (RRPMs) for centrelines around the bend near Annam Road South - Approx 190m.
  11. Installation of a steel rail safety barrier around the tree opposite Bayview Gardens Retirement Living – approximately 20m.

The changes will improve the speed at which motorists travel, keep motorists within their own lane and improve overall road safety for both motorists and pedestrians.

The installation of a cycleway on either side of the proposed raised threshold on Pittwater Road near Cabbage Tree Road will facilitate safe passage for cyclists on the popular road cycling route.

See the detailed plans

Learn how we are managing the works:

Kelbon Pty Ltd will be carrying out these works on behalf of Northern Beaches Council.

Work is scheduled to start in early October and is expected to take approximately 4 weeks to complete, weather permitting.

Work hours are:

  • Monday to Friday, from 7am to 5pm

Traffic control will be onsite to allow pedestrians and all road users to safely pass the work zone. Please drive slowly in the vicinity of the works, and obey all warning signs and directions provided by Traffic Controllers.

Whilst efforts will be deployed to minimise disruption, there will be noise generated from construction activities such as demolition, installation of formwork, and pouring of concrete.

Construction can be disruptive, and we thank you for your patience while we complete this important community project.