Manly CBD - Streetscape Upgrades

We are revitalising Manly CBD through a number of streetscape upgrade projects.
We are revitalising Manly CBD through a number of streetscape upgrade projects.
-
Work postponed due to wet weather
about 1 month agoWork that was scheduled to commence on Monday 26 March along Belgrave Street and Sydney Road, Manly has been delayed due to wet weather and contractor availability. Work will now start after the Easter long weekend.We apologise for the delay in commencing the work and will keep you posted though the usual channels.Work that was scheduled to commence on Monday 26 March along Belgrave Street and Sydney Road, Manly has been delayed due to wet weather and contractor availability. Work will now start after the Easter long weekend.We apologise for the delay in commencing the work and will keep you posted though the usual channels. -
Street Trees - Belgrave Street, Manly
about 1 month agoFollowing a site review of all marked ‘live’ utilities and services along Belgrave Street between Raglan St and Manly Town Hall, we have now developed a plan identifying possible locations for tree installations.
How can I have my say?
We would like your feedback on the possible tree location identified within the plan. If you have any questions, please contact Nathan Innes on 9976 1579.
What size will the trees be?
The new trees will be 200lt with 1.8m of clear trunk before foliage.
Project Timing
Due to the timing required to review possible tree locations, the paving works have been delayed to 26th March (weather permitting).
Following a site review of all marked ‘live’ utilities and services along Belgrave Street between Raglan St and Manly Town Hall, we have now developed a plan identifying possible locations for tree installations.
How can I have my say?
We would like your feedback on the possible tree location identified within the plan. If you have any questions, please contact Nathan Innes on 9976 1579.
What size will the trees be?
The new trees will be 200lt with 1.8m of clear trunk before foliage.
Project Timing
Due to the timing required to review possible tree locations, the paving works have been delayed to 26th March (weather permitting).
-
Belgrave Street Paving Upgrades 2018
4 months agoBetween March and June 2018 we will be undertaking the next stage of the Manly CBD upgrades, with the installation of new granite paving along Belgrave Street.The works will be completed in stages moving along Belgrave Street and consist of:- The removal of street furniture and signage and the demolition of existing pavement.
- The construction and pouring of a concrete binding slab and the rectification of Telstra pits.
- The laying of granite paving.
- The cleaning and sealing of pavers and reinstating street furniture and signage.
There will be minor disruptions to both traffic and pedestrians whilst the works are undertaken. Traffic control will install safety barricades to redirect pedestrians and coordinate temporary parking closures. However, Council and the contractor will be managing this closely to ensure access to businesses and pedestrians is maintained at all times.The project team will work with the contractors and will also be onsite regularly liaising with businesses, the public and residents during the works.If you have any queries contact Nathan Innes on 0410 282 751.
Between March and June 2018 we will be undertaking the next stage of the Manly CBD upgrades, with the installation of new granite paving along Belgrave Street.The works will be completed in stages moving along Belgrave Street and consist of:- The removal of street furniture and signage and the demolition of existing pavement.
- The construction and pouring of a concrete binding slab and the rectification of Telstra pits.
- The laying of granite paving.
- The cleaning and sealing of pavers and reinstating street furniture and signage.
There will be minor disruptions to both traffic and pedestrians whilst the works are undertaken. Traffic control will install safety barricades to redirect pedestrians and coordinate temporary parking closures. However, Council and the contractor will be managing this closely to ensure access to businesses and pedestrians is maintained at all times.The project team will work with the contractors and will also be onsite regularly liaising with businesses, the public and residents during the works.If you have any queries contact Nathan Innes on 0410 282 751.
-
Works have now commenced - Whistler Street
10 months agoPaving upgrade works have now commenced on Whistler Street. Central Avenue will also commence soon.
Works are expected to take approximately 8 – 10 weeks weather permitting.
If you have any queries contact Nathan Innes on 0410282 751.
Paving upgrade works have now commenced on Whistler Street. Central Avenue will also commence soon.
Works are expected to take approximately 8 – 10 weeks weather permitting.
If you have any queries contact Nathan Innes on 0410282 751.
-
Works Commencing - Whistler Street and Central Avenue Streetscape Upgrades, Manly
10 months agoAs part of Revitalise Manly, we are upgrading paving on sections of Central Avenue and Whistler Street.
These works are scheduled to commence 10 July 2017.
These upgrade works will complete links with the previously upgraded Raglan Street, Sydney Road and Manly Corso.
How will these works impact me?
To help minimse disruptions, these works will be delivered in stages.
There will be minor disruptions to both traffic and pedestrian access during these works. Council and the contractor will be working closely to ensure;
- Minimal disruption and access to businesses
- Pedestrian access is maintained
- Businesses receive regular project updates
The completed works will not change current traffic conditions in Whistler Street or Central Avenue however, there may be temporary impact on parking during these works.
Who can I contact during the works?
The project Manager, Nathan Innes will be available onsite regularly or contactable on his below details. The project team will also be onsite regularly liaising with businesses during the works.
Nathan Innes
Project Manager
0410 282 751 or 0405 430 109Contractor: Mansours
0411 366 294 or 9976 1579As part of Revitalise Manly, we are upgrading paving on sections of Central Avenue and Whistler Street.
These works are scheduled to commence 10 July 2017.
These upgrade works will complete links with the previously upgraded Raglan Street, Sydney Road and Manly Corso.
How will these works impact me?
To help minimse disruptions, these works will be delivered in stages.
There will be minor disruptions to both traffic and pedestrian access during these works. Council and the contractor will be working closely to ensure;
- Minimal disruption and access to businesses
- Pedestrian access is maintained
- Businesses receive regular project updates
The completed works will not change current traffic conditions in Whistler Street or Central Avenue however, there may be temporary impact on parking during these works.
Who can I contact during the works?
The project Manager, Nathan Innes will be available onsite regularly or contactable on his below details. The project team will also be onsite regularly liaising with businesses during the works.
Nathan Innes
Project Manager
0410 282 751 or 0405 430 109Contractor: Mansours
0411 366 294 or 9976 1579 -
Tender Contract Awarded
12 months agoOn 26 April 2017, Council awarded the streetscape works contract for Whistler Street and Central Avenue to Mansours Paving Pty Ltd.
To minimise disruption to Manly residents, businesses and visitors, the works will commence once Taste of Manly event has finished in June.
On 26 April 2017, Council awarded the streetscape works contract for Whistler Street and Central Avenue to Mansours Paving Pty Ltd.
To minimise disruption to Manly residents, businesses and visitors, the works will commence once Taste of Manly event has finished in June.
-
Streetscape upgrades - Whistler Street and Central Avenue
12 months agoAs part of Revitalise Manly, we are upgrading paving on Central Avenue and Whistler Street.These upgrade works will complete links with the previously upgraded Raglan Street, Sydney Road and Manly Corso.Watch recording of Council MeetingWhat works will be done?- Paving upgrade
- Landscaping and tree maintenance
- Minor extension of the footpath on the corner of Sydney Road and Whistler Street to improve pedestrian safety
How will these works impact me?We will not be remove parking or changing traffic conditions in Whistler Street or Central Avenue.Access to business frontages will be maintained.For more information, contact Northern Beaches Council on 9976 1500As part of Revitalise Manly, we are upgrading paving on Central Avenue and Whistler Street.These upgrade works will complete links with the previously upgraded Raglan Street, Sydney Road and Manly Corso.Watch recording of Council MeetingWhat works will be done?- Paving upgrade
- Landscaping and tree maintenance
- Minor extension of the footpath on the corner of Sydney Road and Whistler Street to improve pedestrian safety
How will these works impact me?We will not be remove parking or changing traffic conditions in Whistler Street or Central Avenue.Access to business frontages will be maintained.For more information, contact Northern Beaches Council on 9976 1500 -
Background
12 months agoWhistler Street and Central Avenue are the next stage to the Manly CBD upgrade works, with works already completed in The Corso, Raglan Street, Sydney Road, Henrietta Lane and Manly Plaza.The works on Whistler Street and Central Avenue consist of streetscape upgrades, paving treatments, new street furniture and paving to alleviate pedestrian pinch points on pathways.The former Manly Council developed and exhibited the Manly 2015 Masterplan and it was included in the Community Strategic Plan (CSP). The intention of the Masterplan is to build on the existing village character and opportunities that Manly presently enjoys as a vibrant bustling beachside town and tourist destination. The vision for the Manly Masterplan is to ensure that Manly moves into the 21st century as a compact urban village in beautiful natural surroundings and a prosperous, sustainable, vibrant place with improved liveability and community amenity.RFT 2017/034 was issued on 25/02/17 and closed at 2pm on 23/03/17.Whistler Street and Central Avenue are the next stage to the Manly CBD upgrade works, with works already completed in The Corso, Raglan Street, Sydney Road, Henrietta Lane and Manly Plaza.The works on Whistler Street and Central Avenue consist of streetscape upgrades, paving treatments, new street furniture and paving to alleviate pedestrian pinch points on pathways.The former Manly Council developed and exhibited the Manly 2015 Masterplan and it was included in the Community Strategic Plan (CSP). The intention of the Masterplan is to build on the existing village character and opportunities that Manly presently enjoys as a vibrant bustling beachside town and tourist destination. The vision for the Manly Masterplan is to ensure that Manly moves into the 21st century as a compact urban village in beautiful natural surroundings and a prosperous, sustainable, vibrant place with improved liveability and community amenity.RFT 2017/034 was issued on 25/02/17 and closed at 2pm on 23/03/17.
Current Projects
Live Projects
- Voluntary Planning Agreements (Exhibition)
- Road Reserves - Public Exhibition
- Public Exhibition of Leases and Licences
- Queenscliff Parking
- Public Exhibition of Easement Notices
- Dee Why Town Centre Street and Public Open Space Upgrades
- Carpark Review and Rezoning
- Dee Why Town Centre Planning Controls
- Brookvale Vision and Structure Plan
- Boat Trailer Parking Management Plan
- District Park (North Manly) Lease and Development
- Rockpool Renewal (Collaroy)
- Community Strategic Plan SHAPE 2028
- Pittwater Road Conservation Area Review (Manly)
- Church Point Upgrade
- Pittwater Waterway Review
- Mona Vale Place Plan
- Freshwater Coastal Open Space Masterplan
- Unleashed Dog Exercise Areas Review
- Long Reef Surf Club - Renewal
- Mona Vale Surf Club - Renewal
- Bulky Goods Collection
- Glen Street Open Space Masterplan
- Policy Reviews - Public Exhibition - 2017
- Connecting Northern Beaches
- Manly Dam Playplace
- Events Strategy (Draft)
- Planning Proposal - 729-731 Pittwater Road, Dee Why
- Connecting Northern Beaches - Public Art Trail
- Newport Surf Life Saving Club - Building Extensions
- South Narrabeen Surf Life Saving Club - Building Extension
- Creative Art Space
- Planning Proposal - 28 Lockwood Avenue, Belrose
- Library Hours Review
- Tania Park Playground Upgrade
- Planning Proposal - 66 Bardo Road and 2-4 Nooal Street, Newport
- Delivery Program 2018 - 2021
- Minor Amendments to the Manly LEP 2013 (Housekeeping)
- North Narrabeen Rockpool Amenities Upgrade
- Northern Beaches Walking Plan
- Planning Proposal - 1-3 Rodborough Road, Frenchs Forest
- Mona Vale Performance Space
- Annual Financial Statements 2016 - 2017
- Boating facilities upgrade - Rowland Reserve, Bayview
- Berry Reserve Playground Upgrade
- Planning Proposal – 75-79 Old Pittwater Road and 19 Cross Street, Brookvale
- Careel Bay Masterplan
- Sportsground Lighting Upgrade Project 2017/18
- Manly Lagoon Reserve Landscape Plan
- Draft Code of Meeting Practice - 2018
- Narrabeen Lagoon Aquatic Boardwalk
- Bilgola Beach Upgrade 2018
- Move - Northern Beaches Transport Discussion Paper
- Planning Proposal - 114-120 Old Pittwater Road, Brookvale
- Alcohol Free Zones 2018
- Social Housing Open Space Grants 2018
- Contributions Plan 2018 (draft)