IE10 and below are not supported.

Contact us for any help on browser support

Palm Beach Walkway

This consultation has concluded.

Palm Beach Walkway is the first stage of the connected communities project. The walk way will consist of concrete footpaths and elevated boardwalk sections, with custom screening and handrails. The completed project will see planting of new native trees, opportunities for community art and an overall upgrade in safety to the current walking conditions along Barrenjoey Rd. The walkway will be one of a kind and will be another key piece of infrastructure to the Palm Beach area.

Palm Beach Walkway is the first stage of the connected communities project. The walk way will consist of concrete footpaths and elevated boardwalk sections, with custom screening and handrails. The completed project will see planting of new native trees, opportunities for community art and an overall upgrade in safety to the current walking conditions along Barrenjoey Rd. The walkway will be one of a kind and will be another key piece of infrastructure to the Palm Beach area.

This consultation has concluded.
  • Southern End Open

    13 days ago
    Img 2394

    The southern end of the walkway is now open for the public to use.

    We are still fine tuning with touch up's of handrails and replacing plants etc. The walkway now provides a safe pathway from the wharf car park up Barrenjoey Rd.

    Works are continuing along the walkway heading north, with car parking spaces now established at the southern entry of the walkway.

    The privacy screen is almost completed, and lookout works are due to commence in the next few weeks.

    We are working towards handover early August 2018

    The southern end of the walkway is now open for the public to use.

    We are still fine tuning with touch up's of handrails and replacing plants etc. The walkway now provides a safe pathway from the wharf car park up Barrenjoey Rd.

    Works are continuing along the walkway heading north, with car parking spaces now established at the southern entry of the walkway.

    The privacy screen is almost completed, and lookout works are due to commence in the next few weeks.

    We are working towards handover early August 2018

  • Update

    about 2 months ago
    Img 2306

    Installation of the handrail started today at the southern entry point to the walkway.

    Once the timber is installed along the top rail it will look awesome!

    Installation of the handrail started today at the southern entry point to the walkway.

    Once the timber is installed along the top rail it will look awesome!

  • Construction Progress

    2 months ago
    Img 2302

    Site works have progressed down Barrenjoey Rd with construction activities now commenced along the northern stretch of Barrenjoey Rd. You can see the kerb and gutter that has been constructed. These works will continue now until hand over.

    The privacy screen is still being constructed and the general feedback is that everyone is pleased with look and feel of the screen.

    We can't wait for the handrail to go in so that some sections of the walkway can be opened up for the public to use.

    Site works have progressed down Barrenjoey Rd with construction activities now commenced along the northern stretch of Barrenjoey Rd. You can see the kerb and gutter that has been constructed. These works will continue now until hand over.

    The privacy screen is still being constructed and the general feedback is that everyone is pleased with look and feel of the screen.

    We can't wait for the handrail to go in so that some sections of the walkway can be opened up for the public to use.

  • Project Update

    2 months ago
    Img 2271

    Landscaping has commenced at the southern entry point of the walkway. The greenery planted gives us a real insight to how the finished walkway is going to look and feel. We are anticipating the handrails to be delivered to site for installation this month.

    The boardwalk with privacy screen install is continuing up Barrenjoey Rd with works expected to commence at the lookout next month.

    Works are progressing well onsite and we are still working towards a July 2018 opening of the boardwalk.

    Landscaping has commenced at the southern entry point of the walkway. The greenery planted gives us a real insight to how the finished walkway is going to look and feel. We are anticipating the handrails to be delivered to site for installation this month.

    The boardwalk with privacy screen install is continuing up Barrenjoey Rd with works expected to commence at the lookout next month.

    Works are progressing well onsite and we are still working towards a July 2018 opening of the boardwalk.

  • Project Update

    3 months ago

    Works are progressing well along Barrenjoey Rd.

    You can start to see construction of sandstone walls at the southern entry point. The decking on the boardwalk has also started to be installed.

    The construction of the privacy screen has commenced and will continue up Barrenjoey Rd, with the intention of the building works to continue from both north and south and meet in the middle.

    Works are currently forecast to be completed early July.

    Works are progressing well along Barrenjoey Rd.

    You can start to see construction of sandstone walls at the southern entry point. The decking on the boardwalk has also started to be installed.

    The construction of the privacy screen has commenced and will continue up Barrenjoey Rd, with the intention of the building works to continue from both north and south and meet in the middle.

    Works are currently forecast to be completed early July.

  • Design Update

    4 months ago
    Img 2229

    The aesthetic design is now complete, with finishes and fixtures resolved.

    The final design of the walkway uses sandstone edging and paving, timber detailing on the handrails and timber baton screening.

    There will be an abundance of new green plantings as well.

    You can see the design intent on the artist impressions that have been uploaded to this page in the documents tab.

    The aesthetic design is now complete, with finishes and fixtures resolved.

    The final design of the walkway uses sandstone edging and paving, timber detailing on the handrails and timber baton screening.

    There will be an abundance of new green plantings as well.

    You can see the design intent on the artist impressions that have been uploaded to this page in the documents tab.

  • Construction Update

    5 months ago

    Major works have commenced along Barrenjoey Rd as of Monday 29 Jan.

    Contractors will continue to work their way around Barrenjoey Rd from north and southdirections.

    You can expect to see road impacts, whereas excavators will be placed on the road to carry out pile drilling for the walkway. Road impacts will be from 9am to 3pm Monday to Friday.

    We have placed some sample screens along the walkway to get a feel for the proposed screen design and assist us in making design detail decisions. They are samples only and the construction of the screen will be much more...

    Major works have commenced along Barrenjoey Rd as of Monday 29 Jan.

    Contractors will continue to work their way around Barrenjoey Rd from north and southdirections.

    You can expect to see road impacts, whereas excavators will be placed on the road to carry out pile drilling for the walkway. Road impacts will be from 9am to 3pm Monday to Friday.

    We have placed some sample screens along the walkway to get a feel for the proposed screen design and assist us in making design detail decisions. They are samples only and the construction of the screen will be much more robust than the samples.

  • Welcome Back

    5 months ago

    I hope everyone had a great Christmas and New Years break.

    Lloyds Construction are back on site from 8 Jan, working behind barriers and carrying out works with no road impacts until 29 Jan 2018.

    Major works will commence on 29 Jan.

    Looking forward to a great 2018 and a successfull Palm Beach Walkway project being completed this year.

    I hope everyone had a great Christmas and New Years break.

    Lloyds Construction are back on site from 8 Jan, working behind barriers and carrying out works with no road impacts until 29 Jan 2018.

    Major works will commence on 29 Jan.

    Looking forward to a great 2018 and a successfull Palm Beach Walkway project being completed this year.

  • Christmas Period Shut Down

    6 months ago

    Lloyd's Construction will be shutting down the construction site from 21 Dec 2017 to 8 Jan 2108. With no works occurring during this period.

    The northern and southern compound will be retracted to allow for additional parking from 15 Dec 2017 to 29 Jan 2108. There will also be no road impacts from construction activities during this period.

    Wishing everyone a very Merry Christams

    Lloyd's Construction will be shutting down the construction site from 21 Dec 2017 to 8 Jan 2108. With no works occurring during this period.

    The northern and southern compound will be retracted to allow for additional parking from 15 Dec 2017 to 29 Jan 2108. There will also be no road impacts from construction activities during this period.

    Wishing everyone a very Merry Christams

  • Project Update

    6 months ago

    Works are continuing on site with our first 2 driveway integrations poured and stripped this week. Check out the images of the works in the photos tab.

    Landscape design including finishes and fixtures, are being finalised this week. With the aim to have a revised design package and rendered images ready for re-issue early Jan.

    Works are continuing on site with our first 2 driveway integrations poured and stripped this week. Check out the images of the works in the photos tab.

    Landscape design including finishes and fixtures, are being finalised this week. With the aim to have a revised design package and rendered images ready for re-issue early Jan.