Redman Road Plaza Progress Update

24 August 2017

Electrical Works

Electrical Poles

We have now poured footings for the new light pole next to the Master Builders driveway and replaced the leaning pole on the corner of Redman Road and Francis Street.

Ausgrid Network Upgrade

Yesterday, contractors completed the Ausgrid network upgrade.

These works included;

  • Power network adjustment
  • Cut over to new network
  • Removal of overhead poles and wires

Catenary Lighting Feature

We have now poured the eightfootings in preparation for the new catenary lighting feature. The footings will provide the foundations required to stabilise the new structure.

Water Feature

Installation of the pipes and jets for the new water feature have now commenced.

What’s Next?

Concreting

We are now finalising the levels in preparation for the concrete base slab so that paving can commence in September. Following these works, more areas will be made available for public use. This will also reduce the impact whilst works continue.

Tree Planting

Planting of 8 new 6m tall palm trees will commence in September.

Who can I contact if you have any concerns during these works?

If you have any concerns during the works, you can speak directly to the contractors on site, or alternatively, you are welcome to contact Andrew Camarsh on 9942 2385.