Redman Road Plaza Progress Update

9 May 2017

Drainage

Our contractors have now commenced extending the drainage system for Redman Road Plaza. These works will be continuing into next week.

Kerbs and Guttering

Kerb and guttering works are scheduled to commence next week

Project Timing

Due to recent wet weather, there have been some minor delays however the project is still on track to meet expected completion.

Illegal Parking

The illegal parking and turning issue on Redman Road have been addressed with Council and we are currently working to resolve this situation.

Post Office Box

The preparation for relocation of the Australia Post Office Box has commenced. The cement slab has been poured and Australia Post has provided community notification on the post office box outside 2a Redman Road.

The new location will be 70 metres west to Mooramba Rd where it will continue to provide service to the area.

For more information on this, contact Australia Post on 13 13 18.