Construction underway

Project update: March 2024

Freshwater Beach Masterplan works are currently underway.

For public safety the staging of the works requires temporary detours for pedestrians.

The temporary pedestrian detour is expected to be in place until the end of March.

The works include the construction of a new accessible ramp, stairs, handrails and landscaping.

We acknowledge that construction can be disruptive, and we thank you for your patience while we complete this important community project.

Refer to the construction staging timelines and staging plan implementation map below for more details on what's to come.

Temporary pedestrian detour from Moore Rd to Freshwater Beach SLSC

Freshwater beach masterplan pedestrian detour

Construction Staging Timelines

The implementation of the Freshwater Beach Masterplan is a multi-staged programme of work. Refer to the staging plan implementation map below for location of works.
  • Timeline item 1 - active

    Stage 1A: Winter to Spring 2023

    (Timber deck in Stage 1A not until Winter 2024)

  • Timeline item 2 - active

    Stage 1B: Winter to Spring 2023

    (Accessible Ramp picnic settings in Stage 1B not until Autumn 2024)

  • Timeline item 3 - active

    Stage 2: Winter to Spring 2023

    (Ocean front playground in Stage 2 not until Winter 2024)

  • Timeline item 4 - incomplete

    Stage 3: Winter to Spring 2024

  • Timeline item 5 - incomplete

    Stage 4A: 2025

  • Timeline item 6 - incomplete

    Stage 4B: TBD per DA and funding approvals

Revised Staging Plan Implementation

image of the staging plan for the masterplan

Revised staging plan

Engagement outcomes

Following consultation with the community last year, we are pleased to provide the completed Community Engagement Report for this project.

We listened to you and made the following key changes to the overall designs:

  • removal of the sweeping path from Moore Road to the surf club
  • the 'Artful Play' area will now be a simple renewal of the existing playground with some landscaping
  • the main playground has had a variety of modifications based on community feedback, including
    • monkey bars
    • slides
    • nature play and
    • a perimeter fence
  • the staged delivery plan has been developed to ensure efficient delivery in off peak times and to minimise impact to park users.

Check out the revised staging plan and new concept images for the small, ocean front playground where 'Artful Play' was previously included.

Project history

Freshwater Beach and surrounds is a popular destination for local residents and visitors alike. It is often described as a special place that brings the community together.

In 2017-2018 we worked with our community, including a committed project working group, to develop the Freshwater Coastal Open Space Masterplan. This document set out some high level recommendations for upgrading the public open spaces, meeting future recreation needs, improving connectivity and celebrating the heritage of the area.

We recently invited you to view and share your thoughts on the more detailed concept designs for the Freshwater Beach area. These included a new playground, new ramps and shared footpaths, a new public artwork and a new lookout with terraced seating.

The proposed designs look to address general amenity, accessibility, play and maintenance requirements in the Freshwater Beach area. It is the first major renewal of the area to be undertaken since the 1980s.

We used your feedback to finalise the designs and establish a staged implementation plan for the improvements.

The community were invited to complete a comment form, email us and write to us during the consultation period.

Comments were invited from Monday 18 July to Sunday 14 August 2022.

Original concepts