Freshwater Beach is more than just sand and surf - it's where our community comes together. We're working to enhance this special place, and your input has been invaluable every step of the way!
Together, we created the Freshwater Coastal Open Space Masterplan in 2017/18. We shared the detailed designs in 2022, and asked for your thoughts before we began works in 2023 to bring our shared vision to life.
This is the first major renewal since the 1980s, and we're addressing general amenity, accessibility, play areas and maintenance needs.
Completed stages
Click on the coloured icons to learn about each item
New playground coming soon - southern end
We are renewing the playground at the southern end (Moore Road) with new equipment and surfacing, including:
- new play structure for toddlers
- new swing set with standard, toddler & basket seats
- dune buggy spring rocker
- new synthetic grass safety surfacing
- slight repositioning of playground and path as outlined in the masterplan.
The playground will be of a similar size to the existing, and will meet current Australian Standards.
Updated timeline
Works have commenced with the removal of the old playground and construction of the new connect path. Due to a delay in shipment of playground equipment, we've had to adjust construction schedules. We anticipate the renewal works will commence 12 January 2026 (subject to weather and contractor availability).
FAQs
Frequently asked questions
Project updates
Project updates
The final pieces of equipment have been installed at the accessible playground and features facilities the whole family will enjoy, including:
| Play in motion: | Body strength, coordination, and dexterity: | Additional features: |
|---|---|---|
|
|
|





A brand new accessible playground has opened, offering an exciting and inclusive play space for children of all abilities. Designed with a captivating underwater theme that celebrates local marine life, the playground promises adventure and sensory exploration.
Children will be thrilled by the diverse range of play equipment, including:
- An engaging slide
- Interactive sensory and musical elements
- Challenging monkey bars
- Classic swings
- An exciting spinner
- Somersault bars
- A comprehensive climbing area
- A charming nature trail
Safety and comfort were paramount in the playground's design. New shade sails provide protection from the sun, while a secure fence ensures children can play freely without wandering near busy roads. The thoughtfully landscaped area features elegant sandstone seating, lush grassed spaces, a soft safety surface, improved pathways, and convenient BBQ facilities.
This playground isn't just a play area—it's a vibrant, welcoming community space that invites children to explore, imagine, and connect with their environment.
The new playground was proudly funded by the NSW Government through the Metropolitan Greenspace Program.
Project update: September 2024
We've refreshed the line markings in the Freshwater Beach car park to improve parking accessibility.

Project update: July 2024
Picnic shelters
Two new picnic shelters have been installed near the beach playground.

BBQs
Two new accessible BBQs have been installed and are open for use.

Stairs
All stair/ramp tactiles and stair nosings have been installed.

Lookout deck
The new lookout deck is complete for the community to enjoy, complete with plantings and garden beds.
Village Playground
The playground construction at Freshwater Beach Park will begin on 15 July and is expected to be completed by November 2024. Refer to the map for the affected area.

Project update: June 2024
Picnic Shelters
Two new picnic shelters have been installed at Freshwater Beach along Moore Road (green markers).
Another two shelters have been installed near the beach playground (red markers).

Project update: April 2024
Freshwater Beach Masterplan works continue as we revitalise the precinct for our community to enjoy.
The new accessible ramp, stairs, handrails, and landscaping have now been completed. Temporary fencing will remain in place as we let the new turf areas establish and grow.
The new timber lookout deck and construction of the new playground will begin mid-2024.
We are planning to start shortly on new picnic shelters, seating and bbq's.
We acknowledge that construction can be disruptive, and we thank you for your patience while we complete this important community project.
Refer to the construction staging timelines and staging plan implementation map below for more details on what's to come.
Project update: March 2024
Freshwater Beach Masterplan works are currently underway.
For public safety the staging of the works requires temporary detours for pedestrians.
The temporary pedestrian detour is expected to be in place until the end of March.
The works include the construction of a new accessible ramp, stairs, handrails and landscaping.
We acknowledge that construction can be disruptive, and we thank you for your patience while we complete this important community project.
Refer to the construction staging timelines and staging plan implementation map below for more details on what's to come.
Project update: December 2023
Works on the initial stages of the Freshwater Beach Masterplan implementation are well underway. Construction commenced in September 2023 and will continue into early 2024 (weather permitting).
The works included in this stage are:
- new wider footpaths
- accessible paths
- new timber deck lookout platform - deferred to Winter 2024
- extra trees and plantings
- sandstone walls
- new seating, showers and picnic tables
- new bbq’s, bike racks and drinking fountains.
Refer to the construction staging timelines and staging plan implementation map below for more details on what's to come.
2022 Engagement outcomes
Freshwater Beach Masterplan: You spoke, we listened!
From 18 July to 14 August 2022, you shared your ideas through:
- Online comment forms
- Emails
- Letters
Thanks to your feedback we've made some exciting changes to our plans.
What's Changed
- Removed the path from Moore Road to the surf club
- Simplified the 'Artful Play' area - we'll refresh the existing playground with new landscaping
- Updated the main playground based on your suggestions:
- Added monkey bars and slides
- Included nature play elements
- Added a perimeter fence for safety
Planning for smooth delivery
We've created a revised staging plan to:
- Work during off-peak times
- Minimise disruption to park users.
Document library
Document links
-
Freshwater Coastal Open Space Masterplan
Back to main pageFreshwater Beach Amenities Building
Learn moreHave an enquiry?
Contact Information Name Major Infrastructure Projects Phone 1300 434 434 (during business hours) Email council@northernbeaches.nsw.gov.au In writing 'Freshwater Beach Masterplan Implementation' Northern Beaches Council, PO Box 82, Manly NSW 1655.
Contact customer service on:
1300 434 434
We
acknowledge the Traditional Custodians and their Country on which we
gather today. By these words we show our respect to all Aboriginal
people. We acknowledge Elders past, present and emerging and the spirits
and ancestors of the Clans that lived in this area.
Connect with us on social media