Project update

October 2024

Project snapshot

DA 2021/2173 history

Development Application (DA 2021/2173) for the proposed works at Newport Life Saving Club was lodged in early November 2021.

Submissions on the Development Application were notified and invited between 19 November and Friday 10 December 2021.

DA 2021/2173 notification period closed: 5pm, Friday 10 December 2021.

Outcome of DA

DA 2021/2173 was refused by the Sydney Northern Beaches Planning Panel in October 2022, and a subsequent Review of Determination was submitted but has not been determined by the Panel.

Council appealed the Panel’s refusal of the Development Application in the Land and Environment Court. The Court has granted leave for Council to rely on an amended Development Application (DA 2021/2173 - LEC2023/109048).

Submissions to the Panel Secretariat on the amended application were notified and invited exhibition between 22 August and 4 September 2024.

Submissions closed 4 September 2024.

Engagement history

We worked with Newport Surf Life Saving Club on a proposed building extension plan which was first exhibited in August 2017.

The plan was based on a masterplanning concept commissioned by the Newport Surf Life Saving Club to address the need for increased storage and floor space as well as improve access.

A revised concept was exhibited between Thursday 26 November 2020 and Thursday 21 January 2021, we received 328 submissions.

The building extension concept plan addressed the need to maintain the important heritage elements, provide increased floor space and improve access.

Feedback revealed a high level of overall support for the proposed refurbishment and extension. Comments that were unsupportive of the concept cited excessive size, mismatch with the building's heritage and modern look of the new extension.

Themes that arose included:

  • overall support
  • facilities improvement
  • heritage
  • architectural design
  • community usage
  • café/restaurant
  • safety/accessibility
  • seawall
  • growth

Engagement outcomes are detailed in the community and stakeholder engagement report.

Concepts

The building extension concept plan provides a design that addressed the need to maintain the important heritage elements, provide increased floor space and improve access.

Key design features include:

  • increased equipment storage
  • a new internal lift, foyer and improved circulation
  • two dedicated training rooms with secondary access
  • extension of north facing terrace
  • grouping amenities
  • a buried seawall

  • Ground floor

    First floor

    Size

    Size

    Foyer

    49m2

    Main hall

    103m2

    Storage

    312m2

    Observatory

    30m2

    First Aid

    9m2

    Balcony and terrace

    130m2

    Lifeguards space

    9m2

    Amenities

    22m2

    Administration office

    20m2

    Bar and kitchen

    26m2

    Club amenities

    50m2

    Committee room

    66m2

    Public amenities

    55m2

    Training area

    100m2

    Shop / BBQ

    12.5m2

    Bicycle racks

    8

    Concept in detail

    Concept addresses coastal impacts

    Coastal engineering investigations indicate that the existing rock revetment is inadequate to ensure long term stability of the coastal zone and a seawall is required to mitigate the risk of undermining of the surf club building from coastal erosion and recession due to sea level rise.

    To address this risk coastal protection works will be implemented as part of this project in the form of a buried seawall along the length of the building.

    Based on historical sand level records at Newport Beach and sea level rise scenarios over a 60 year design life, the seawall would remain mostly buried under long term recession and not be visible.

    Artists impressions are provided below, indicating three possible scenarios.

    Timeline

    • Timeline item 1 - complete

      Mid 2019: Engineering investigations commence

    • Timeline item 2 - complete

      Mid-late 2019: Develop coastal protection strategy

      (based on geotechnical findings)

    • Timeline item 3 - complete

      Early-mid 2020: Develop concept design

      (addressing heritage concerns)

    • Timeline item 4 - complete

      Late 2020: Exhibit concept design

    • Timeline item 5 - complete

      Late 2021: Design progress to Development Application stage

    • Timeline item 6 - complete

      Late 2022: Notice of Determination

    • Timeline item 7 - complete

      Late 2022: Review of Determination lodged

    • Timeline item 8 - complete

      Aug 2024: Exhibition of revised DA

    • Timeline item 9 - active

      Late 2024: Development application determination

    Have an enquiry?

    Have questions or want to learn more about this project, contact us below:

    Name Bernard Koon
    Phone 1300 434 434
    Email council@northernbeaches.nsw.gov.au
    Website www.northernbeaches.nsw.gov.au
    In writing

    Northern Beaches Council, PO Box 82, Manly NSW 1655.

    Stage 1 engagement history